1. Assume U.S. GAAP (generally accepted accounting principles) applies unless otherwise noted. A company entered into a three-year construction project with a total contract price of $5.3 million and expected cost of $4.4 million. The following table provides cash flow information relating to the contract:

 

 

Year 1

Year 2

Year 3

Costs incurred and paid

$600,000

$3,000,000

$800,000

Amounts billed and payments received

$1,200,000

$2,800,000

$1,300,000

What is the cumulative effect of the contract on the cash balance that would have been recorded on the company's balance sheet at the end of Year 2 using the:

 

percentage-of-completion method?

completed contract method?

A.

$400,000

$400,000

B.

$400,000

$0

C.

$2,800,000

$0

Correct answer = A  The amount of cash recorded is identical for both methods and is equal to the total cash received less total costs incurred. At the end of Year 2, a total of $4 million had been billed and collected but only $3.6 million in costs had been incurred.  
 

無論用哪種會(huì)計(jì)方法,并不影響現(xiàn)金流,影響的只是利潤的確定?,F(xiàn)金流是按照真實(shí)的現(xiàn)金流入流出來確定的。*9年的現(xiàn)金流量表上有現(xiàn)金的流入$600,000,第二年有現(xiàn)金流出$200,000,所以在第二年年末的時(shí)候現(xiàn)金流量表上的余額是$400,000。
 

  
  掃一掃微信,*9時(shí)間獲取2014年CFA考試報(bào)名時(shí)間和考試時(shí)間提醒
  
  
  高頓網(wǎng)校特別提醒:已經(jīng)報(bào)名2014年CFA考試的考生可按照復(fù)習(xí)計(jì)劃有效進(jìn)行!另外,高頓網(wǎng)校2014年CFA考試輔導(dǎo)高清網(wǎng)絡(luò)課程已經(jīng)開通,通過針對(duì)性地講解、訓(xùn)練、答疑、???,對(duì)學(xué)習(xí)過程進(jìn)行全程跟蹤、分析、指導(dǎo),可以幫助考生全面提升備考效果。

  報(bào)考指南:2014年CFA考試備考指南
  免費(fèi)題庫:2014年CFA免費(fèi)題庫
  考前沖刺:CFA備考秘籍
  高清網(wǎng)課:CFA考試網(wǎng)絡(luò)課程