USCPA沖刺備考階段,練題時(shí)不要忘記多練一些綜合題哦。高頓網(wǎng)校USCPA小編搜集了一些USCPA的綜合大題,供考生們練習(xí)。
  Golden, Inc. began operation of its construction division on October 1, year 1, and entered into contracts for two separate projects. The No.1 project contract price was $600,000 and provided for penalties of $10,000 per week for late completion.
  Although during year 2 the No.1 project had been on schedule for timely completion, it was completed four weeks late in August year 3. The No.2 project’s original contract price was $800,000. Change orders during year 3 added $40,000 to the original contract price. The following data pertains to the separate long-term construction projects in progress:
                                                                                           No.1              No.2
  As of September 30, year 2:
  Costs incurred to date                                                      $360,000        $410,000
  Estimated costs to complete                                              40,000           410,000
  Billings 315,000 440,000 Cash collections                            275,000         365,000
  As of September 30, year 3: Costs incurred to date            450,000          720,000
  Estimated costs to complete – 180,000 Billings                    560,000          710,000
  Cash collections                                                                560,000           625,000
  Additional information
  - Golden accounts for its long-term construction contracts using the percentage-of-completion method for financial reporting purposes and the completed-contract method for income tax purposes.
  - Enacted income tax rates are 25% for year 2 and 30% for future years.
  - Golden’s income before income taxes from all divisions, before considering revenues from long-term construction projects, was $300,000 for the year ended September 30, year 2. There were no other temporary or permanent differences.
  Prepare a schedule showing Golden’s gross profit (loss) recognized for the years ended September 30, year 2, and year 3,under the percentage-of-completion method. Golden Inc.
  SCHEDULE OF GROSS PROFIT (LOSS)
  For the Year Ended September 30, year 2:
  Estimated gross profit (loss):                                         No.1             No.2
  Contract price
  Less total costs
  Estimated gross profit (loss)
  Percent complete:
  Costs incurred to date
  Total costs
  Gross profit (loss) recognized
  For the Year Ended September 30, year 3: Estimated
  gross profit (loss):
  Contract price
  Less total costs
  Estimated gross profit (loss)
  Percent complete:
  Costs incurred to date
  Total costs
  Percent complete
  Gross profit (loss) recognized
  Less gross profit (loss) recognized in prior year
  Gross profit (loss) recognized
  Answer:
  No.1                   No.2
  $600,000         $800,000
  $400,000         $820,000
  $200,000         ($20,000)
  \                           \
  $360,000         $410,000
  $400,000         $820,000
  $180,000         ($20,000)
  $560,000         $840,000
  $450,000         $900,000
  $110,000         ($60,000)
  \                           \
  $450,000         $720,000
  $450,000         $900,000
  100%              80%
  $110,000        ($60,000)
  $180,000        ($20,000)
  ($70,000)       ($40,000)