以下是高頓網(wǎng)校小編為學(xué)員整理的:p3商務(wù)分析,供學(xué)員參考。
 
  FIGURE 4: THE CONTROL STAGE
  However, certain priorities or pressures are likely to apply to each variable, depending on the nature of the project. For example, a project involving safety-critical systems will rightly put great emphasis on quality because the consequence of technical failure will be very serious. However, managers need to be aware of the impact of the following compromises:
  · Increased emphasis on quality places the project in danger of taking longer and costing more.
  · Increased emphasis on meeting the cost budget may compromise quality, the project may take longer, or the scope could be narrowed.
  · Increased emphasis on meeting time deadlines may also compromise quality, cost over-runs are more likely (perhaps because overtime has to be paid), or scope could be narrowed.
  · If the emphasis is to ensure that the project scope is not reduced, then cost and time might increase, and quality might decrease. Naturally, if scope is increased, whether through project drift or through more pre-meditated changes to the project, costs, time and quality will all be severely jeopardised.
  None of these compromises is bound to happen, but project managers should be aware that such tensions exist and that a balance has to be maintained by management action, if necessary negotiating with the project sponsors to gain approval for changes.
  PROJECT PLANNING AND MANAGEMENT TOOLS
  Typically, projects consist of a number of separately identifiable steps which can be broken down, hierarchically, until manageable work packages are produced which can be assigned to the appropriate people. This is the process of deriving the work breakdown structure for the project. Each work package, or task, will have four components:
  · task name and description
  · costs, both marginal and any fixed element
  · duration
  · who is responsible and, in particular, whether the work will be carried out internally or externally.
  So now the project manager knows who is doing what and how much each element should cost. Using a relatively simple cost accounting system, material, labour, overheads and third party costs can be coded to the work packages, hence to the project, and actual costs can be compared to budget for control purposes.
  Still to be taken into account is the time that each work package will take, but whereas costs are cumulative, times need not be as often several tasks can be undertaken simultaneously. A more sophisticated approach is needed which sets out the relationship of the tasks or activities to one another, identifying those tasks which can be concurrent and those which can only be consecutive. For example, if the project was to set up a new website for the company, the task of choosing the internet service provider to host the website can be undertaken at the same time as designing the graphics and layout of the web pages. However, the layout and graphics couldn’t be finalised before the company has decided what information the web pages should show. These three tasks could be set out in a network diagram, or critical path analysis, as shown in Figure 5.
 
  高頓網(wǎng)校小編寄語:努力了,就無怨無悔。有道是:天道籌勤!相信自己,你是最棒的!

   ACCA官方微信    
  掃一掃微信,*9時間獲取2014年ACCA考試報名時間和考試時間提醒
  
  高頓網(wǎng)校特別提醒:已經(jīng)報名2014年ACCA考試的考生可按照復(fù)習(xí)計劃有效進行!另外,高頓網(wǎng)校2014年ACCA考試輔導(dǎo)高清課程已經(jīng)開通,通過針對性地講解、訓(xùn)練、答疑、???,對學(xué)習(xí)過程進行全程跟蹤、分析、指導(dǎo),可以幫助考生全面提升備考效果。
  
  報考指南:2014年ACCA考試備考指南
  免費題庫:2014年ACCA考試免費題庫
  考前沖刺:ACCA備考秘籍
  高清網(wǎng)課:ACCA考試網(wǎng)絡(luò)課程